When will it be done?
Generate a realistic schedule for your project.
Create a realistic phase-by-phase timeline for your home improvement project. Plan for demolition, rough-ins, and finishes.
Estimated Completion
Monday, April 27, 2026
Total Duration: 7 Weeks
Based on
Estimated Completion
Total Duration: 7 Weeks
Tear out, site protection, dumpster.
3/9/2026 - 3/15/2026
Framing, plumbing, electrical, HVAC.
3/16/2026 - 3/29/2026
Insulation, drywall, tape, texture, flooring.
3/30/2026 - 4/5/2026
Cabinets, trim, paint, fixtures, appliances.
4/6/2026 - 4/19/2026
Final touch-ups, inspections, cleaning.
4/20/2026 - 4/26/2026
Disclaimer: This tool is for informational and planning purposes only and does not constitute professional financial, construction, or safety advice. Actual costs, ROI, and material requirements may vary significantly based on location, market conditions, and site specifics. Construction projects involve inherent safety risks; always follow local building codes, use appropriate safety gear, and consult with licensed professionals (engineers, electricians, contractors) for complex or structural work. The creators of this tool are not liable for project outcomes, injuries, or financial losses.
Total Duration
Weeks = BaseDuration × ComplexityMultiplier
Phase Duration
PhaseWeeks = TotalWeeks × PhaseRatio
Completion Date
Date = StartDate + (TotalWeeks × 7)
Continue your journey with these related tools
Key Insights & Concepts
The #1 complaint homeowners have about contractors is "they are taking too long." But often, the expectation was unrealistic to begin with.
A quality renovation is a manufacturing process that happens inside your house. Unlike a factory, every condition is unique, and materials don't always arrive on time.
Why is nobody working on your house today?
These are the items that stop the entire project if they aren't ready:
8-12 week lead time. If you wait until demo starts to order cabinets, you will have a gutted kitchen for 3 months. Order them first!
Custom sizes take 6-10 weeks. You can't stucco/side the exterior until they are installed.